01/01/2011

 

Verso Paper

Scheck's largest job for Verso Paper in Sartell, Minnesota is the annual Major Boiler shutdown. Scheck Industrial, demonstrating its consistent job performance has been awarded the contract four of the last five years, with the latest being the summer of 2010. Scheck has been awarded both maintenance and capital jobs for Verso Paper in 2011. In addition to the piping and boiler work Scheck has performed Millwright construction on Verso's Paper Machine vacuum pumps, in their Coal Handing Area and had repaired one of the Mill's dam tainter gates in the first part of August.


Below are some of the projects Scheck
has done for Verso Paper in 2011:

Coal Handling Conveyor Repairs
PM3 – Vacuum Pump 2 & 5 Replacement
PM3 – Couch Vacuum Pump Replacement
#1 Dam Tainter Gate Repairs