Scheck Industrial has completed several maintenance and capital jobs for Boise White Paper in 2011. The largest being a HPP code job for the #3 Turbine Generator 170# Extraction Steam Piping Project, both Phase I and Phase II. Scheck Industrial has demonstrated its' flexibility and ability to manage multi-disciplined trades by performing Millwright work on Boise's paper machines during minor shutdowns and in other areas of the Mill.

 

Below are some of the projects Scheck has done for Boise White Paper in 2011:

 

Scheck Industrial commends the Project Team for their great work at Boise:
Jim Keenan – Project Manager
William Karo - Pipefitter Superintendent
Tom Needham – Pipefitter Foreman